The approval of Question 2 on the special election ballot means this project will move forward.
Remodel for improved safety and security of building entrances and traffic.
$1.5 million budget for remodel
THE building timeline
Design Planning - Spring, 2018
Groundbreaking - Spring, 2019
Anticipated Construction Completion - Fall, 2019
what's happening at forestview now
Fall 2019: Project Completed
March 27, 2019: Forestview Middle School Main Entrance and Site Improvements project bids opened. Advertisement for bids can be found here. See approved bidder information here.
March 4, 2019: Board of Education approved Construction Documents and authorized construction manager to solicit bids
February 11, 2019: Board of Education approved Schematic Design plans
October 29, 2018: Update on Baxter Schools Traffic Study (Board of Education approved Option #2)